The lower raft foundation is now complete, and the team is currently installing and tying the reinforcement steel across the raft.
You can also see the column dowels already projecting upward. These vertical bars will connect the raft foundation to the structural columns of the building above.
Once the reinforcement steel installation is finished, the upper raft concrete will be poured, which completes the foundation stage. After that, the project will move into the ground floor structure.
Good progress on site this week. We’ll continue sharing short updates as the building takes shape.